null Does an employer with an asbestos removal license have to submit the measurement data on the negative pressure monitoring of compartments to the builder or another party steering or supervising the construction project without a separate request?

Does an employer with an asbestos removal license have to submit the measurement data on the negative pressure monitoring of compartments to the builder or another party steering or supervising the construction project without a separate request?

Asbestos

Monitoring measurement data is attached to the cleanliness verification document after asbestos removal without a separate request.